title: "Legalizing it: the after-the-fact permit, the inspection"
description: "An after-the-fact permit is an ordinary permit filed for work already done; the city reviews drawings, inspects the open and hidden parts, and signs off."
url: "https://shinnslist.com/courses/unpermitted-additions/upa-06-legalizing-it-the-after-the-fact-permit-the-inspection-and"
---

> An after-the-fact permit is an ordinary permit filed for work already done; the city reviews drawings, inspects the open and hidden parts, and signs off.

[Unpermitted Additions and Basement Bedrooms in Colorado: Free Course](/courses/unpermitted-additions/) Light or dark

[Free Courses](/courses/) › [Unpermitted additions course](/courses/unpermitted-additions/) › [Going deeper](/courses/unpermitted-additions/#u3) › Lesson 6

# Legalizing it: the after-the-fact permit, the inspection and what can go wrong

Going deeper · 1 study hours

**Read once:** This course is general education, not legal, tax, lending or appraisal advice. Every dollar figure here is an example; a real house turns on that house, that city's code office and your own lender.

**Bottom line:** An after-the-fact permit is an ordinary permit filed for work already done; the city reviews drawings, inspects the open and hidden parts, and signs off only when the work meets the code in force today, so budget for opening walls, re-doing hidden work and a few surprises.

**Bottom line first.** Legalizing unpermitted work means asking the building department for a permit after the fact, letting an inspector see the work (including what is behind drywall), fixing whatever fails and getting a final sign-off. It is routine. What goes wrong is almost always one of three things: the work is judged against today's code rather than the code when it was built, hidden work has to be exposed, or the permit is left open and never finaled.

### Which code applies

A city judges an after-the-fact permit against the code it has adopted now, not the code in force when the work was done. Denver, for example, adopted the 2025 Denver Building and Fire Codes on June 13, 2025, incorporating the 2024 I-codes, with second-printing updates adopted on November 24, 2025 (Denver Community Planning and Development, Building Codes page). A basement finished in 2012 to the then-current rules may still fail a 2026 inspection on alarms, arc-fault protection or egress. That is not the inspector being difficult; it is the only code they are allowed to apply.

### The steps

- **Apply.** File a permit application describing the work as built, with a simple floor plan. Some cities let the owner of an owner-occupied house pull the permit (Denver publishes **homeowner permit** rules; Denver Building Codes page). If a contractor pulls it, the contractor controls it: at the Pikes Peak Regional Building Department, for example, homeowners cannot schedule an inspection if a contractor obtained the permit (PPRBD home page).
- **Plan review.** Staff check the drawings against code: ceiling height, egress, bathroom venting, alarm locations. They may ask for more detail or an engineer's letter for anything structural.
- **Expose and inspect.** The inspector must see framing, wiring, plumbing and insulation. Expect to cut **inspection holes** in drywall or ceilings where the hidden work runs. Rough-in inspections happen with the walls open; the final happens when everything is closed and finished.
- **Correct.** A failed item comes back as a **correction notice**: a written list of what to fix before re-inspection. Fix it, request another inspection.
- **Final.** The permit is **finaled** (closed as passed). Keep the final inspection record; it is what you hand the next buyer and appraiser.

Scheduling is mundane but matters. At PPRBD, inspections are requested online or by phone with the permit number, and weekdays at 8:30 am is the cutoff for same-day scheduling (PPRBD home page). Miss the cutoff and your contractor sits idle a day.

### What goes wrong

- **Hidden work fails.** Open splices, undersized wiring, no vapor barrier, a drain with the wrong slope. You find out only after the drywall is cut.
- **Scope grows.** Legalizing a bedroom means the whole room must pass, which can pull in the furnace room next to it or the stair.
- **The permit sits open.** An owner finishes the fixes, never calls the final, and the permit expires or is cancelled (Denver lists an application and permit cancellation procedure on its Building Codes page). An open or cancelled permit is a red flag on the next sale.
- **Zoning, not building.** If the space was used as a separate rental unit, the building department may route you to zoning before issuing anything.
- **Stop-work risk.** Doing more unpermitted fixes before the permit is issued invites a stop-work order and a complaint record.

### Example with real numbers

Larkspur Court in Denver, after closing. Priya bought the 3/1 with the unpermitted 980-square-foot basement for $510,000 (lesson 5) and now wants a legal 4/2. Every figure here is made up for the example. She starts from Marcus's $22,500 of bids (lesson 4) and tracks what actually happens.

| Step | Budgeted | Actual | Note |
| --- | --- | --- | --- |
| Permit, drawings, fees | $2,400 | $2,400 | Owner pulled a homeowner permit |
| Egress window and well | $7,500 | $7,500 | Passed first rough inspection |
| Duct reroute | $3,200 | $3,200 | Passed |
| Electrical | $2,800 | $4,100 | Inspection holes found two more buried junction boxes |
| Alarms | $900 | $900 | Passed |
| Plumbing | $3,600 | $5,200 | Ejector pit vent had to be run to the roof |
| Drywall, patch, paint | $2,100 | $2,900 | More holes than planned |
| **Total** | **$22,500** | **$26,200** | $3,700 over, about 16% |

Her risk discount in lesson 5 was $5,600, so the overrun stayed inside what she priced. Timeline: application to final took 11 weeks, two failed inspections (electrical and plumbing), one re-inspection each. The permit was finaled and she saved the record.

Value check on the lesson 3 comps: a legal 4/2 around $545,000 against $510,000 + $26,200 = $536,200 in, roughly $8,800 of value created rather than the $12,500 she hoped for. Still positive, and the house now appraises and insures as what it is. If the electrical had needed a full rewire (a $12,000 made-up bid she was quoted as the worst case), she would have been about $400 under water on the project. That worst case is why lesson 5's risk discount exists.

Next lesson: how this finaled permit changes the price, disclosure, appraisal and insurance when she sells, and what happens to the neighbor who never legalized.

## Law cited

- Denver Community Planning and Development: Building Codes, Policies and Guides
- Pikes Peak Regional Building Department

## Key terms

After-the-fact permit A permit applied for after work is already done; the city reviews and inspects the existing work. Homeowner permit A permit the owner of an owner-occupied house pulls personally instead of a licensed contractor, where the city allows it. Plan review The building department's desk check of drawings against the adopted code before a permit is issued. Inspection hole A cut in finished drywall or ceiling so the inspector can see hidden framing, wiring or plumbing. Rough-in inspection An inspection done while walls are open, before insulation and drywall. Correction notice The inspector's written list of items that failed and must be fixed before re-inspection. Finaled A permit closed as passed after the final inspection. Stop-work order A city order halting construction until a permit is obtained or a violation is fixed. Adopted code The edition of the building code a city has formally made law; after-the-fact work is judged against it.

## Flashcards

### Which code edition applies to an after-the-fact permit?

The code the city has adopted now, not the one in force when the work was done.

### When did Denver adopt the 2025 Denver Building and Fire Codes?

June 13, 2025, incorporating the 2024 I-codes.

### At PPRBD, who can schedule an inspection on a contractor-pulled permit?

The contractor; homeowners cannot.

### PPRBD cutoff for same-day inspection scheduling?

Weekdays at 8:30 am.

### What is a correction notice?

The inspector's written list of failed items to fix before re-inspection.

### What does 'finaled' mean?

The permit is closed as passed after the final inspection.

### Larkspur Court: budgeted vs actual to legalize?

$22,500 budgeted, $26,200 actual, $3,700 over.

### Larkspur Court: weeks from application to final?

11 weeks, with two failed inspections.

### Larkspur Court: value created after legalizing at $26,200?

About $8,800 ($545,000 - $536,200).

### Biggest reason hidden work costs more than bid?

You cannot see it until inspection holes are cut.

## Quiz: 10 questions

Tap an answer. It shows right or wrong and opens the reason. Your score is saved in this browser and counts in the [study app](/courses/unpermitted-additions/study).

- An after-the-fact permit is judged against:
**A** The code in force when the work was built
- **B** The code the city has adopted today
- **C** Whichever code is cheaper to meet
- **D** No code; it is only a records update

### Show answer and why

**Answer: B.** The code the city has adopted today

Inspectors can only apply the currently adopted code.

Denver Community Planning and Development: Building Codes, Policies and Guides

- Denver adopted the 2025 Denver Building and Fire Codes on:
**A** January 1, 2024
- **B** November 24, 2025
- **C** June 13, 2025
- **D** June 13, 2021

### Show answer and why

**Answer: C.** June 13, 2025

The June 13, 2025 adoption incorporated the 2024 I-codes; November 24, 2025 was the second-printing update.

Denver Community Planning and Development: Building Codes, Policies and Guides

- At the Pikes Peak Regional Building Department, if a contractor obtained the permit, who may schedule inspections?
**A** The contractor who purchased the permit
- **B** Either the homeowner or the contractor
- **C** Only the homeowner
- **D** Only the real estate agent

### Show answer and why

**Answer: A.** The contractor who purchased the permit

PPRBD states homeowners cannot schedule an inspection if a contractor obtained the permit.

Pikes Peak Regional Building Department

- PPRBD's weekday cutoff for same-day inspection scheduling is:
**A** Noon
- **B** 5:00 pm the day before
- **C** 7:00 am
- **D** 8:30 am

### Show answer and why

**Answer: D.** 8:30 am

Weekdays at 8:30 am is the cutoff; routes are then set geographically.

Pikes Peak Regional Building Department

- Why are inspection holes cut during an after-the-fact permit?
**A** To install new insulation
- **B** To lower the ceiling
- **C** So the inspector can see hidden wiring, plumbing and framing
- **D** To check paint color

### Show answer and why

**Answer: C.** So the inspector can see hidden wiring, plumbing and framing

The inspector must see the work behind finished surfaces.

Lesson text

- A correction notice is:
**A** A refund of permit fees
- **B** The inspector's list of failed items to fix before re-inspection
- **C** A zoning variance
- **D** A property tax appeal

### Show answer and why

**Answer: B.** The inspector's list of failed items to fix before re-inspection

It is the written fail list; you fix it and request re-inspection.

Lesson text

- Larkspur Court: budgeted $22,500, actual $26,200. The overrun is:
**A** $2,200
- **B** $5,600
- **C** $4,700
- **D** $3,700

### Show answer and why

**Answer: D.** $3,700

26,200 - 22,500 = 3,700, about 16%.

Larkspur Court example (made up)

- Larkspur Court: $510,000 purchase plus $26,200 to legalize, against $545,000 comps, creates about:
**A** $8,800
- **B** $12,500
- **C** $35,000
- **D** $0

### Show answer and why

**Answer: A.** $8,800

510,000 + 26,200 = 536,200; 545,000 - 536,200 = 8,800.

Larkspur Court example (made up)

- An owner finishes all fixes but never requests the final inspection. The permit:
**A** Closes automatically as passed
- **B** Converts to a certificate of occupancy
- **C** Stays open and may expire or be cancelled, a red flag on resale
- **D** Is refunded

### Show answer and why

**Answer: C.** Stays open and may expire or be cancelled, a red flag on resale

Denver lists a permit cancellation procedure; an open or cancelled permit does not prove the work passed.

Denver Community Planning and Development: Building Codes, Policies and Guides

- Larkspur Court: Priya's lesson 5 risk discount was $5,600. Her actual overrun of $3,700 was:
**A** Larger than the discount
- **B** Within the discount
- **C** Exactly equal to it
- **D** Not related to it

### Show answer and why

**Answer: B.** Within the discount

3,700 is less than 5,600, so the risk discount covered the surprise.

Larkspur Court example (made up)

[← Buying and selling it: the disclosure form and pricing the same house both ways](/courses/unpermitted-additions/upa-05-buying-and-selling-it-the-disclosure-form-and-pricing-the)[Buying or selling a house with unpermitted work: price, disclosure, appraisal and insurance →](/courses/unpermitted-additions/upa-07-buying-or-selling-a-house-with-unpermitted-work-price)

## After you study